March ARB Building 100 Massive Change Order

We issued our abatement project report today on Building 100 at the March Air Reserve Base. Due to asbestos survey blunders by others, the abatement was greatly delayed while an approximately $250,000 change order was negotiated by the general contractor, our Client. We monitored and documented the abatement project after completing the follow-on asbestos survey in February of 2011 (see News article below).